Demo: Dynamic Job Plans in Maximo

Read our blog: What's New in Maximo 7.6.1.1.

Dynamic job plans in IBM Maximo

Dynamic Job Plans allow users to calculate resources needed per unit of work. Job Plans can now turn into work orders that accurately allocate all resources needed proportionally.

Additionally, work orders created from Job Plans can be calculated in three different ways:

  • Static (job plan quantity/duration applied directly to order)
  • Proportional (multiplying units for a given work order/asset combination)
  • Level (select quantity/duration based on pre-defined thresholds – ex. Any work order over five miles in length requires two foreman). 

Dynamic Job plans are available for users with Maximo 7.5.0.0 and up. Is your Maximo system out of date? Learn more about virtual Maximo upgrades.